What is the timeline for the 2022 Corteva Carbon Initiative process?
Sign up anytime before August 31, 2022 - Onboarding
- Sign Carbon contract
- Corteva Field Team will help:
- Establish your Granular Insights account, if needed
- Upload field boundaries into Granular Insights
- Verify field boundaries in Granular Insights
June-July 2022 - Enrollment
-
Complete Enrollment:
- Select fields with a qualifying practice change
- Complete eligibility questions
- Declare practice change(s)
Late Summer 2022 - Data Set Up & Historical Needs
-
Enter historical crop rotation data
-
Confirm carbon boundaries
-
Set up Machine Data Connection (if not already established)
Post-Harvest 2022 - Activities & Supporting Evidence
-
Enter required field data, including historical and current field activities
-
Meet Dec 1 deadline to:
- Add new boundaries
- Answer eligibility questions
- Enter field practice changes
Jan-Feb 2023 - Submission & Validation
- Verify accuracy and functionality of all field data
- Submit all required data to Granular Insights for initial review by Feb 1
- Submit Final File to Indigo by Feb 15 to generate a carbon payment
Other Important Milestones
March-April 2023 - Randomized Soil Sampling
Your CSM will contact you if any field(s) on your operation are chosen for randomized soil sampling. Sampling will be done by an outside vendor at no cost to you.
Fall 2023 - Payment
You will receive payment for your carbon impact based on the program vesting schedule.